(1) Each boiler must be equipped with a pressure gauge directly connected to the steam space of the drum. Pressure gauges should be installed in front of the feed water regulating valve, the outlet of the separable economizer, the outlet of the superheater and the main steam valve.
(2) For boilers or pressure vessels with high-temperature steam as the working medium, a water trap should be installed on the connection pipe of the pressure gauge to make the steam condense in this section of the elbow to prevent high-temperature steam from directly entering the spring tube of the pressure gauge, causing The components in the gauge are overheated and deformed, which affects the accuracy of the pressure gauge. When steel pipe is used for water trap, its inner diameter shall not be less than 10mm. A three-way cock should be installed between the pressure gauge and the water trap to facilitate the flushing of the pipeline, removal and replacement, and calibration of the pressure gauge.
(3) According to the maximum allowable pressure of the boiler or pressure vessel, draw a warning red line on the dial of the pressure gauge. However, the warning red line should not be drawn on the glass of the pressure gauge, so as to avoid the illusion of the glass rotation and cause an accident.
(4) For pressure vessels containing high-temperature, highly corrosive or high-viscosity media, a liquid-filled isolation device should be installed on the connecting pipeline between the pressure gauge and the vessel, or an anti-corrosion corrugated flat diaphragm pressure gauge should be used.
(5) The location where the pressure gauge is installed should have sufficient lighting to facilitate observation and inspection by the operator. To prevent the pressure gauge from being affected by radiant heat, low temperature and vibration.
(6) In order to facilitate the replacement and calibration of the pressure gauge, a three-way cock should be installed between the pressure gauge and the pressure-bearing equipment. The cock should be installed on the vertical pipe section, and there should be an opening mark and a locking device.